(BARTLETT) City of Bartlett Water Valve Project Update:
City staff met with the City Engineer’s office and the contractor this afternoon to put together the first weeks schedule for the valve project starting next Monday.
Thursday, 2/26 and/or Friday, 2/27- Exploratory “pot-holing” with NO expected water outage-
• Emma/Jackson Street intersections
•SW Front Street/Pietzch Street intersection
•SE Front Street/Pietzch Street intersection
—
Monday, 3/2/26 CITY WIDE WATER OUTAGE starting at 8 a.m.
•Replacing valves at Emma/Jackson Street
•Replacing valves at SW Front Street/Pietzch Street
•Replacing valves at SE Front Street/Pietzch Street
Water will be turned back on after valves are replaced daily!
—
Tuesday, 3/3/26 Exploratory “pot-holing” with NO expected outage
• Multiple locations along West Elm Street
• West Jackson Street at prison tower
• West Clark Street/Emma Street
• West Aisne Street/Emma Street
—
Wednesday, 3/4/26 CITY WIDE WATER OUTAGE starting at 1 p.m.
•Replace valves, multiple locations along West Elm Street
•Replace valve on West Jackson Street and prison tower
Water will be turned back on after valves are replaced daily!
—
Thursday, 3/5/26 CITY WIDE WATER OUTAGE starting at 1 p.m.
• Replace valves at West Clark Street/Emma Street
Water will be turned back on after valves replaced daily!
—
Friday, 3/6/26- TBD If Water is shut off, it will be after 1 p.m.
• Replace valves at Water plant- suction side
• Replace valves at West Aisne/Emma Street
Water will be turned back on after valves replaced daily!
—
We will push these updates out weekly throughout the project and do our absolute best to minimize the water outages to as few as possible. We thank you for showing grace to City Staff, our contractors and everyone involved during this project!
Please reach out to Adrian Flores at City Hall with any questions or concerns @ 254-527-3219 or Mayor Chad Mees @ 817-219-5160.
—–